North Bay City Council has approved a payment in the amount of $29,879 (plus HST) to Tambeau Construction Ltd. for services rendered for the Dionne Quints Home move.
The funds will be transferred to Tambeau to bridge the gap between the estimate of $147,750 and the $180,087 that the move and construction at the new site ultimately cost, an increase of $32,337.
City Council approved the move of the Dionne Home to the green space between the Discovery North Bay Museum and Marina Point Retirement Village in April 2017. This is when the estimate of $147,750 had originally been formulated. Funding was to come from the sale of the land on which the home used to sit, near the defunct Tourism Centre.
The move of the Dionne Home cost $57,475, the construction of a vapour extraction system and foundation came in at $59,078.36, plus another $21,634.80 for a new electrical service. Another $4,169 was spent to increase the height of the foundation to facilitate future building systems for the structure and tarping and heating the foundation to allow for masonry work added another $2,705.05.
Therefore, Tambeau’s original contract totalling $59,078.36 increased to $87,587.21. This amount is beyond the CAO’s approval authority so Council had to approve the amount.
The work is nearly completed from the move and foundation aspects. According to the staff report, landscaping has not been discussed with Dionne Quints Heritage Board and costs are yet to be determined. If minor landscaping is agreed upon, the cost will be absorbed into the Parks budget.